After years of preparation, Florensis realized a new production facility for young plants in Dinteloord in 2019 under the guidance of AAB.
After the foundation had already been realized at the end of 2018, the entire greenhouse with installations was built up on schedule and put into use in phases between week 12 and week 52 2019. At the same time, the water technical room, the boiler house, the business premises, the water basin and the pavement have been prepared.
For this project, AAB has taken care of the purchase of the plot, the permit work and the project management during the design and implementation phase.
See below for two movies and the photos of the result: